Fire/Paramedic Station Project Description
Includes the purchase of a 1-acre site and construction of a 15,250-sq.
ft. Standard Fire/Paramedic Station.

New Fire Station 78 |
|
Fire Facility Location
Currently, Fire Station 78 is located in a
temporary facility at 4230 Coldwater Canyon Ave.
Surveys and cost analysis were conducted to locate a new 1-acre
parcel to meet the operational needs for this project. The new
location is 4041 N. Whitsett Ave.
 |
Current Progress
Architect: Robbins Jorgensen Christopher, Inc.
Phase: Complete
|
|
Tentative
Schedule
| Property Acquisition |
September 2001 - August 2005 |
| Design Phase |
September 2003 - May 2005 |
| Contractor Bid & Award Process |
May 2005 - July 2006 |
| Construction Phase |
July 2006 - September 2008 |
|